Initial Site Investigation
Our involvement includes:
- Review the property and carry out a preliminary inspection and BCA audit
- Take Needs Analysis from client to confirm proposed space allocations for new tenancy including student and staff numbers, classroom sizes, breakout space, labs, etc.
- Identify Project Goals to ensure team alignment with our clients objectives
- Provide a report of findings based on property reviews/audits
- Identify suitability of property for 9b compliance
- Highlight compliance issues that may impact Change of Use and project costings
- Identify heritage listings or other property development limiting factors
- Provide Key Takeaways and recommendations to maximise the probability of a successful Change of Use application while minimising the risk of substantial additional non-compliance costs.
- Review local council Local Environmental Plan for the area
- Review Section 149 to confirm if alternative change of use can be achieved
Increase Occupancy Numbers Analysis
Our scope of works includes:
-
Review the property and carry out a preliminary inspection and BCA audit
-
Take Needs Analysis from client to confirm proposed space allocations for refurbished tenancy including student and staff numbers, classroom sizes, breakout space, labs, etc.
-
Review existing egress and identify possible limitations in this area
-
Develop strategies to overcome occupancy numbers based on egress limitations
-
Review existing amenities and identify possible limitations in this area
-
Provide a recommended solution to overcome limitations in the area of amenities
-
Review current allowable operating hours as per the existing Development Application
-
Recommend possible increase to operation hours to help in revenue uplift
-
Highlight any other compliance issues that may impact project outcomes
-
Provide solutions and recommendations to allow for the increased occupancy numbers.
-
Review Section 149 to confirm ongoing approval process.
-
Provide a report of findings based on occupancy review/audit


Increase Occupancy Numbers Analysis
Our Scope Of Works includes:
Design Process
-
Interview and prepare selected design teams to pitch for project work
-
Arrange and host design presentations
-
Review design presentations and fee proposals and make recommendations
-
Work with appointed design team through space planning, concept design and design development
Development Application:
-
Prepare DA (Development Application including arranging owner’s sign off)
-
Prepare Statement of Environmental Effects
-
Prepare Plan of Management
-
Arrange BCA report (if required)
-
Pre-DA lodgement meeting with Council (if required)
-
Submit DA application to Council
-
Manage DA through Council process
note: no guarantee of a successful Council approval or Council conditions
Construction Certificate:
-
Prepare CC (Construction Certificate) application forms
-
Arrange for CC application forms to be signed
-
Arrange Design Certificates from Head Contractor and service trades
-
Arrange and attend Pre-CC site inspection
-
Submit CC application to Building Surveyor
-
Issue CC to allow commencement of fit-out works
Occupation Certificate:
-
Arrange for OC (Occupation Certificate) application forms to be signed
-
Arrange and attend Pre-OC site inspection
-
Arrange Certificates of Compliance from Head Contractor and service trades
-
Submit OC application to Building Surveyor
-
Issue OC to client
Disbursements associated with the Certification Package including:
-
Insurances
-
Town planner
Project Management Package
Our Scope Of Works includes:
Design Process:
-
Work with appointed design team through concept design and design development documentation
-
Work with services consultants to facilitate design and documentation for mechanical, fire protection, electrical and hydraulic if required OR
-
Work with head contractors to develop a Design and Construct option for selected services if possible
-
Provide accurate budget based on approved sketch plans and concept design
-
Work with design team to rework concepts etc as required to meet approved budget
-
Look at innovative solutions to provide project outcomes to match client affordability
-
Work with design team to facilitate certification drawings
-
Work with design team to facilitate tender drawings
Tender Process:
-
Review tender documentation including plans, schedules and specifications
-
Manage fit-out contractor tender including:
-
Issue Requests for Quotation
-
Arrange and attend site inspections
-
Manage and issue Requests for Information
-
Compile and review tender submissions
-
Prepare tender review reports for client
-
Arrange and chair tender review meeting/s
-
Review client/contractor contract
-
develop “value engineering” options to facilitate cost effective solutions where possible
-
Construction Process:
-
Facilitate kick off meeting with successful Head Contractor team and client
-
Undertake full set out with Head Contractor to ensure compliance with approved plans.
-
Provide cloud base Project Management and Communications system to ensure clarity of the project schedule and the achievement of key project mile stones.
-
Attend regular Project Control Meetings (PCM’s) to ensure project time lines, compliance requirements and quality standards are met
-
Manage additional and approved variation process
-
Review contractor progress invoices, approve and submit for payment
-
Arrange and conduct defects inspections per stage
-
Facilitate solutions for onsite issues and problems
-
Monitor correction of defects and outstanding items before hand over of each stage.
-
Facilitate client hand over on completion of project